Renovation Timeline

November 30 Mid-December: Workers will be removing carpet and applying wall and floor finishes on the first floor. Visitors to the library should be aware that fumes, dust and noise will result from this work. Completed

Children's Department


Watch video of the RollerGirls helping
with the Children's renovation

November 1 November 8: Our Children's Services will be closed as they move into their Outpost in Rooms 1B and 1C. You should plan on visiting the Ellettsville Branch or the Bookmobile for your children's reading needs during this period. Children's movies and some children's music will be available in our Movies and Music area on the 1st floor during this time. Completed

November 9: Children's Services will reopen in Rooms 1B and 1C with a limited collection and limited services while their space is renovated. Children's movies and music will remain in our Movies and Music area during this time. Completed

January 24 January 31, 2010: The Children’s Outpost in IB and IC will close as we move back into our renovated space. During this week Children's DVDs will be available in our Movies & Music Department. Homework Help will continue to operate out of Room 1A and there will be a small browsing collection of Children's books available in the Atrium. Completed

February 1, 2010: The renovated Children's Department will reopen. Come and see our wonderful new space! Completed

1st Floor Circulation

November 6, 2009: The Checkout Desk on the 1st floor will close. We will move checkout to a temporary space in our atrium. During this time you will be able to return and check-out materials. You will be asked to go to the 2nd floor Checkout Desk for the payment of fines and fees that are not done at the Express Check stations. Completed

February 1, 2010: The Checkout Desk will reopen in our newly renovated space. Completed

February 28, 2010: Please join us between 2:00 and 3:00 to celebrate the completion of the 1st floor renovations.

Drive-up and Parking Lot Work

November 18 25: Driving lanes and parking spot changes:


November 6 7: Our parking lot will be closed for excavation and curb work. Completed

January – March, 2010:  New curb cuts on Kirkwood and in our parking lot as well as a new bicycle parking area on the NW corner of the building will be created. Completed

January – March, 2010: Grant Street drainage work and sidewalk repairs will reduce flooding potential. Completed

January – Late March, 2010:  Excavation and construction work will continue in our parking lot as a new Drive-through lane is created.   Parking on the east side of our lot will be restricted until this work is completed.

ADULT SERVICES, VITAL AND EL CENTRO

Early February 2010: Work will begin on the 2nd floor. The first stages will create a new circulation area & new VITAL tutoring spaces. Work on the new Drive-up will also continue during this time.

February 3, 2010: El Centro reopens in Room 1A. Completed

February 4 & 5, 2010: VITAL will close as they move into their temporary home in Room 1C. Completed

February 6, 2010: The VITAL Office will reopen in 1C where tutors will meet their students. Completed

March 1, 2010:  Spanish and Asian DVDs and CDs will be moved downstairs to “Movies and Music” as construction begins in the northwest corner of the 2nd floor where our new circulation department will be located.  Spanish print materials will move to the shelves east of the VITAL office doorway. Completed

March 8, 2010 – May, 2010:  Shelving movers will begin relocating shelving to clear space for carpeting that will be installed later in March and April.  The process of moving shelves will continue on through March and April as new flooring is installed throughout the 2nd floor.  Access to collection areas will be restricted during the moving process but patrons may ask for assistance from staff at the Information Desk.  They may also return later that day if they wish to browse the collection.  Seating areas, shelving, computer carrels and gathering spaces will move and change throughout this period of time.

Early April, 2010: Circulation services on the 2nd floor will move into their new location.  Our new Drive-through lane in the parking lot will open as the Grant Street Drive-through closes.  The new Drive-through   will be open all hours the library is open.

Early April, 2010:  VITAL and El Centro offices will be relocated from the 1st floor to the 2nd floor.